Back to jobs
RW-25-0409RE-FLOW

Brackenridge bridge - bearing replacement

Client
Penwith Hollow Borough Council
Service
Bridges and structures
Manager
Alun Morvane
Status
Closed
Start
6 Oct 2025
Finish
9 Oct 2025
Order value
£590
No flags
SAGESYRINXJOINEDInternal plant hire in Sage equals the Syrinx charges for this job to 30 Sep 2026: difference £0.00

Money

SAGE
Invoiced to date£590.00
5000 Materials£17.39
5100 Subcontract£9.29
5200 Direct labour£1,627.00
5300 Plant hire - internal£350.00
5310 Plant hire - external£3.17
5400 Fuel£4.33
5500 Haulage and tipping£6.14
Cost to date£2,017.32
Margin(241.9%)(£1,427.32)

Kit

SYRINX
6 hires, £350 charged
MovementAssetDescriptionOn hireOff hireDaysDay rateChargeInspection in date every day out
MV-10027TL-0294110V diamond core drill6 Oct 20259 Oct 20254£20.00£80.00Yes
MV-10028TL-0525Podium step6 Oct 20259 Oct 20254£11.00£44.00Yes
MV-10029TL-0153Hydraulic breaker6 Oct 20259 Oct 20254£22.00£88.00Yes
MV-10030TL-0236Petrol cut-off saw 300mm6 Oct 20259 Oct 20254£20.00£80.00Yes
MV-10031LG-041Harness with fall arrest lanyard6 Oct 20259 Oct 20254£7.00£28.00Yes
MV-10032LG-199Chain sling 2-leg6 Oct 202510 Oct 20255£6.00£30.00Yes
Total (6 records)£350.00

Site: who worked on it

RE-FLOW
DatePersonRoleCards heldCards valid that dayBooking
6 Oct 2025Iolo PellowTM operativeCSCS, Lantra NHSS 12CYesWorked
6 Oct 2025Bethan FarrantCoatings applicatorCSCS, Working at heightYesWorked
7 Oct 2025Niall GethinOperativeCSCS, First aid at work, Working at height, Abrasive wheels, PASMAYesWorked
7 Oct 2025Osian DewhurstPlant operatorCSCS, NPORS, Working at height, IPAFYesWorked
8 Oct 2025Gwion QuarrellOperativeCSCS, Working at height, Abrasive wheelsYesWorked
8 Oct 2025Elis VarleyOperativeCSCS, Working at height, Abrasive wheels, PASMAYesWorked
9 Oct 2025Iolo ColebrookGang foremanCSCS, NRSWA street works, SMSTS, Confined spaces, Working at height, Abrasive wheels, IPAFYesWorked
9 Oct 2025Osian VarleyCoatings applicatorCSCS, First aid at work, Working at heightYesWorked

Site: forms

RE-FLOW
22 forms, 1 unsigned
FormTypeDateJobPersonDetailSignedGPS
F-100128RAMS briefing sign-on6 Oct 2025RW-25-0409Iolo PellowYes51.8795, -3.0700
F-100129RAMS briefing sign-on6 Oct 2025RW-25-0409Bethan FarrantYes51.8792, -3.0691
F-100130Daily timesheet6 Oct 2025RW-25-0409Iolo Pellow9 hoursYes51.8792, -3.0693
F-100131Daily timesheet6 Oct 2025RW-25-0409Bethan Farrant8 hoursYes51.8796, -3.0701
F-100132Daily site diary6 Oct 2025RW-25-0409Iolo PellowYes51.8791, -3.0693
F-100133Toolbox talk6 Oct 2025RW-25-0409Iolo PellowFatigueYes51.8796, -3.0686
F-100134Pre-use check6 Oct 2025RW-25-0409Bethan FarrantTL-0294Yes51.8795, -3.0700
F-100135Pre-use check6 Oct 2025RW-25-0409Bethan FarrantTL-0525Yes51.8795, -3.0700
F-100136Pre-use check6 Oct 2025RW-25-0409Bethan FarrantTL-0153Yes51.8795, -3.0700
F-100137Pre-use check6 Oct 2025RW-25-0409Bethan FarrantTL-0236Yes51.8795, -3.0700
F-100138Pre-use check6 Oct 2025RW-25-0409Bethan FarrantLG-041Yes51.8795, -3.0700
F-100139Pre-use check6 Oct 2025RW-25-0409Bethan FarrantLG-199No51.8795, -3.0700
F-100180Daily timesheet7 Oct 2025RW-25-0409Osian Dewhurst9 hoursYes51.8801, -3.0696
F-100181Daily timesheet7 Oct 2025RW-25-0409Niall Gethin8 hoursYes51.8791, -3.0702
F-100182Daily site diary7 Oct 2025RW-25-0409Osian DewhurstYes51.8802, -3.0696
F-100222Daily timesheet8 Oct 2025RW-25-0409Gwion Quarrell8 hoursYes51.8802, -3.0695
F-100223Daily timesheet8 Oct 2025RW-25-0409Elis Varley9 hoursYes51.8789, -3.0690
F-100224Daily site diary8 Oct 2025RW-25-0409Gwion QuarrellYes51.8790, -3.0703
F-100265Daily timesheet9 Oct 2025RW-25-0409Iolo Colebrook9 hoursYes51.8792, -3.0699
F-100266Daily timesheet9 Oct 2025RW-25-0409Osian Varley9 hoursYes51.8786, -3.0685
F-100267Daily site diary9 Oct 2025RW-25-0409Iolo ColebrookYes51.8786, -3.0689
F-100268Job completion9 Oct 2025RW-25-0409Osian Varley17 photosYes51.8804, -3.0684