RW-25-0425RE-FLOW
Redwater culvert - CCTV survey and clean
- Client
- Tier-1 Highways Partner A
- Service
- Drainage CCTV
- Manager
- Alun Morvane
- Status
- Closed
- Start
- 14 Oct 2025
- Finish
- 18 Oct 2025
- Order value
- £2,890
No flags
SAGESYRINXJOINEDInternal plant hire in Sage equals the Syrinx charges for this job to 30 Sep 2026: difference £0.00
Money
SAGE| Invoiced to date | £2,890.00 | |
| 5000 Materials | £71.98 | |
| 5100 Subcontract | £50.73 | |
| 5200 Direct labour | £1,770.00 | |
| 5300 Plant hire - internal | £1,267.00 | |
| 5310 Plant hire - external | £16.08 | |
| 5400 Fuel | £18.62 | |
| 5500 Haulage and tipping | £25.72 | |
| Cost to date | £3,220.13 | |
| Margin | (11.4%) | (£330.13) |
Kit
SYRINX| Movement | Asset | Description | On hire | Off hire | Days | Day rate | Charge | Inspection in date every day out |
|---|---|---|---|---|---|---|---|---|
| MV-10092 | TL-0207 | Petrol cut-off saw 300mm | 14 Oct 2025 | 19 Oct 2025 | 6 | £10.00 | £60.00 | Yes |
| MV-10093 | PL-081 | Diesel pump 4in | 14 Oct 2025 | 19 Oct 2025 | 6 | £25.00 | £150.00 | Yes |
| MV-10094 | TL-0397 | 110V transformer | 14 Oct 2025 | 18 Oct 2025 | 5 | £11.00 | £55.00 | Yes |
| MV-10095 | PL-173 | Mini excavator 3t | 14 Oct 2025 | 19 Oct 2025 | 6 | £167.00 | £1,002.00 | Yes |
| Total (4 records) | £1,267.00 |
Site: who worked on it
RE-FLOW| Date | Person | Role | Cards held | Cards valid that day | Booking |
|---|---|---|---|---|---|
| 14 Oct 2025 | Niall Gethin | Operative | CSCS, First aid at work, Working at height, Abrasive wheels, PASMA | Yes | Worked |
| 14 Oct 2025 | Harri Larkham | Operative | CSCS, First aid at work, Working at height, Abrasive wheels | Yes | Worked |
| 15 Oct 2025 | Iolo Pellow | TM operative | CSCS, Lantra NHSS 12C | Yes | Worked |
| 15 Oct 2025 | Eira Jessop | Drainage and CCTV operative | CSCS, Confined spaces, Working at height, IPAF | Yes | Worked |
| 16 Oct 2025 | Hywel Oakhurst | Operative | CSCS, First aid at work, Working at height, Abrasive wheels | Yes | Worked |
| 16 Oct 2025 | Eira Jessop | Drainage and CCTV operative | CSCS, Confined spaces, Working at height, IPAF | Yes | Worked |
| 17 Oct 2025 | Harri Larkham | Operative | CSCS, First aid at work, Working at height, Abrasive wheels | Yes | Worked |
| 17 Oct 2025 | Tomos Oakhurst | Drainage and CCTV operative | CSCS, First aid at work, Confined spaces, Working at height, IPAF | Yes | Worked |
Site: forms
RE-FLOW| Form | Type | Date | Job | Person | Detail | Signed | GPS |
|---|---|---|---|---|---|---|---|
| F-100502 | RAMS briefing sign-on | 14 Oct 2025 | RW-25-0425 | Harri Larkham | Yes | 52.1087, -3.5364 | |
| F-100503 | RAMS briefing sign-on | 14 Oct 2025 | RW-25-0425 | Niall Gethin | Yes | 52.1074, -3.5369 | |
| F-100504 | Daily timesheet | 14 Oct 2025 | RW-25-0425 | Harri Larkham | 10 hours | Yes | 52.1082, -3.5379 |
| F-100505 | Daily timesheet | 14 Oct 2025 | RW-25-0425 | Niall Gethin | 8 hours | Yes | 52.1092, -3.5362 |
| F-100506 | Daily site diary | 14 Oct 2025 | RW-25-0425 | Harri Larkham | Yes | 52.1092, -3.5369 | |
| F-100507 | Toolbox talk | 14 Oct 2025 | RW-25-0425 | Harri Larkham | Weil's disease | Yes | 52.1081, -3.5377 |
| F-100508 | Permit to dig | 14 Oct 2025 | RW-25-0425 | Harri Larkham | Yes | 52.1084, -3.5369 | |
| F-100509 | Pre-use check | 14 Oct 2025 | RW-25-0425 | Niall Gethin | TL-0207 | Yes | 52.1087, -3.5364 |
| F-100510 | Pre-use check | 14 Oct 2025 | RW-25-0425 | Niall Gethin | PL-081 | Yes | 52.1087, -3.5364 |
| F-100511 | Pre-use check | 14 Oct 2025 | RW-25-0425 | Niall Gethin | TL-0397 | Yes | 52.1087, -3.5364 |
| F-100512 | Pre-use check | 14 Oct 2025 | RW-25-0425 | Niall Gethin | PL-173 | Yes | 52.1087, -3.5364 |
| F-100560 | Daily timesheet | 15 Oct 2025 | RW-25-0425 | Iolo Pellow | 10 hours | Yes | 52.1085, -3.5363 |
| F-100561 | Daily timesheet | 15 Oct 2025 | RW-25-0425 | Eira Jessop | 10 hours | Yes | 52.1081, -3.5371 |
| F-100562 | Daily site diary | 15 Oct 2025 | RW-25-0425 | Iolo Pellow | Yes | 52.1088, -3.5379 | |
| F-100631 | Daily timesheet | 16 Oct 2025 | RW-25-0425 | Hywel Oakhurst | 10 hours | Yes | 52.1087, -3.5369 |
| F-100632 | Daily timesheet | 16 Oct 2025 | RW-25-0425 | Eira Jessop | 10 hours | Yes | 52.1080, -3.5371 |
| F-100633 | Daily site diary | 16 Oct 2025 | RW-25-0425 | Hywel Oakhurst | Yes | 52.1076, -3.5370 | |
| F-100680 | Daily timesheet | 17 Oct 2025 | RW-25-0425 | Harri Larkham | 10 hours | Yes | 52.1091, -3.5373 |
| F-100681 | Daily timesheet | 17 Oct 2025 | RW-25-0425 | Tomos Oakhurst | 9 hours | Yes | 52.1093, -3.5373 |
| F-100682 | Daily site diary | 17 Oct 2025 | RW-25-0425 | Harri Larkham | Yes | 52.1093, -3.5374 | |
| F-100683 | Job completion | 17 Oct 2025 | RW-25-0425 | Tomos Oakhurst | 18 photos | Yes | 52.1079, -3.5373 |