RW-25-0485RE-FLOW
Hatherleigh Cross footbridge - steel repaint
- Client
- Thornbury Marsh County Council
- Service
- Industrial coatings
- Manager
- Eira Upcott
- Status
- Closed
- Start
- 17 Nov 2025
- Finish
- 18 Nov 2025
- Order value
- £2,010
No flags
SAGESYRINXJOINEDInternal plant hire in Sage equals the Syrinx charges for this job to 30 Sep 2026: difference £0.00
Money
SAGE| Invoiced to date | £2,010.00 | |
| 5000 Materials | £50.14 | |
| 5100 Subcontract | £35.11 | |
| 5200 Direct labour | £925.00 | |
| 5300 Plant hire - internal | £273.00 | |
| 5310 Plant hire - external | £15.29 | |
| 5400 Fuel | £14.91 | |
| 5500 Haulage and tipping | £19.85 | |
| Cost to date | £1,333.30 | |
| Margin | 33.7% | £676.70 |
Kit
SYRINX| Movement | Asset | Description | On hire | Off hire | Days | Day rate | Charge | Inspection in date every day out |
|---|---|---|---|---|---|---|---|---|
| MV-10329 | LG-167 | Round sling 2t | 17 Nov 2025 | 18 Nov 2025 | 2 | £6.00 | £12.00 | Yes |
| MV-10330 | PL-090 | Submersible pump 2in | 17 Nov 2025 | 18 Nov 2025 | 2 | £41.00 | £82.00 | Yes |
| MV-10331 | TM-2006 | Keep left sign set | 17 Nov 2025 | 18 Nov 2025 | 2 | £7.00 | £14.00 | Yes |
| MV-10332 | PL-108 | Trench rammer | 17 Nov 2025 | 19 Nov 2025 | 3 | £20.00 | £60.00 | Yes |
| MV-10333 | PL-207 | Welder generator 300A | 17 Nov 2025 | 19 Nov 2025 | 3 | £35.00 | £105.00 | Yes |
| Total (5 records) | £273.00 |
Site: who worked on it
RE-FLOW| Date | Person | Role | Cards held | Cards valid that day | Booking |
|---|---|---|---|---|---|
| 17 Nov 2025 | Gwion Quarrell | Operative | CSCS, Working at height, Abrasive wheels | Yes | Worked |
| 17 Nov 2025 | Geraint Quarrell | Plant operator | CSCS, NPORS, Working at height, PASMA | Yes | Worked |
| 18 Nov 2025 | Eira Ashdown | Operative | CSCS, Working at height, Abrasive wheels, PASMA | Yes | Worked |
| 18 Nov 2025 | Iolo Pellow | TM operative | CSCS, Lantra NHSS 12C | Yes | Worked |
Site: forms
RE-FLOW| Form | Type | Date | Job | Person | Detail | Signed | GPS |
|---|---|---|---|---|---|---|---|
| F-102017 | RAMS briefing sign-on | 17 Nov 2025 | RW-25-0485 | Geraint Quarrell | Yes | 52.2000, -2.9551 | |
| F-102018 | RAMS briefing sign-on | 17 Nov 2025 | RW-25-0485 | Gwion Quarrell | Yes | 52.2004, -2.9548 | |
| F-102019 | Daily timesheet | 17 Nov 2025 | RW-25-0485 | Geraint Quarrell | 10 hours | Yes | 52.1987, -2.9553 |
| F-102020 | Daily timesheet | 17 Nov 2025 | RW-25-0485 | Gwion Quarrell | 9 hours | Yes | 52.1993, -2.9560 |
| F-102021 | Daily site diary | 17 Nov 2025 | RW-25-0485 | Geraint Quarrell | Yes | 52.2002, -2.9559 | |
| F-102022 | Toolbox talk | 17 Nov 2025 | RW-25-0485 | Geraint Quarrell | Silica dust | Yes | 52.2003, -2.9559 |
| F-102023 | Pre-use check | 17 Nov 2025 | RW-25-0485 | Gwion Quarrell | LG-167 | Yes | 52.2000, -2.9551 |
| F-102024 | Pre-use check | 17 Nov 2025 | RW-25-0485 | Gwion Quarrell | PL-090 | Yes | 52.2000, -2.9551 |
| F-102025 | Pre-use check | 17 Nov 2025 | RW-25-0485 | Gwion Quarrell | TM-2006 | Yes | 52.2000, -2.9551 |
| F-102026 | Pre-use check | 17 Nov 2025 | RW-25-0485 | Gwion Quarrell | PL-108 | Yes | 52.2000, -2.9551 |
| F-102027 | Pre-use check | 17 Nov 2025 | RW-25-0485 | Gwion Quarrell | PL-207 | Yes | 52.2000, -2.9551 |
| F-102101 | Daily timesheet | 18 Nov 2025 | RW-25-0485 | Eira Ashdown | 9 hours | Yes | 52.1995, -2.9563 |
| F-102102 | Daily timesheet | 18 Nov 2025 | RW-25-0485 | Iolo Pellow | 9 hours | Yes | 52.2002, -2.9564 |
| F-102103 | Daily site diary | 18 Nov 2025 | RW-25-0485 | Eira Ashdown | Yes | 52.2005, -2.9558 | |
| F-102104 | Job completion | 18 Nov 2025 | RW-25-0485 | Iolo Pellow | 15 photos | Yes | 52.1993, -2.9567 |